Safety & Radioprotection
4 sub-tasks
Task 5: Safety & Radioprotection
schedule
4y (D) Conformity to legislation
3y (C) Decommissioning (B) Radioactivity control, safety & risks
2y
1. 2. 3. 4. 5. 6. 7. 8.
Participants: GANIL, France FZJ, Germany LMU, Germany CERN, EU CEA, France NIPNE, Romania FI, Lithuania Univ. Warsaw, Poland
role - sub-task D - sub-task C - sub-task B - sub-task A - coordination - contribution - contribution - contribution
External partners: ORNL, ANL, TRIUMF, JAERI, KAERI
(A) Radiation, activation, shielding & doses
15 June 2006, PSI, Switzerland; contact:
[email protected]
1y
Safety & Radioprotection
2006: sub-task A
• radiation characterization (primary beam, targets, beam dump, secondary beam lines) • activation estimates (primary and secondary beam lines, targets, beam dump, environment) • optimization of shielding against prompt radiation, dose rates
** Deliverable/
** Deliverable/Milestone Name
Milestone No
** Workpackage
** Lead
/Subtask No
Contractor(s)
** Planned in months
Expected in months
M1.1
Validation of MC codes
5/A
CERN, CEA, NIPNE, WU, FI
6
12 1 OK
M1.2
Radiation & activation estimates
5/A
CERN, CEA, NIPNE, WU, FI
12
36 1 ?
M1.3
Shielding guidelines
5/A
CERN, CEA, NIPNE, WU, FI
22
22 1 OK
15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task A; M1.1; validation of MC codes
TN-06-01 "Validation of FLUKA calculated cross-sections for radioisotope production in proton-ontarget collisions at proton energies around 1 GeV“, M. Felcini, A. Ferrari, CERN, January 2006
TN-06-02 "Monte-Carlo validation on accelerator shielding experiments“, A. Plukis, A. Zukauskaite, R. Plukiene, FI Vilnius , Jan. 2006
TN-06-04 “Benchmark calculations on particle production within the EURISOL DS project ” , B. Rapp, J.C. David , V. Blideanu, D. Doré, D. Ridikas, N. Thiolliere, CEA Saclay, March 2006
OK 1 Recommendations/improvements for both MCNPX and FLUKA 15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task A; M1.2; radiation and activation
TN-06-05 “Radiotoxic and conventional toxic inventories of an Hg target“, R. Moorman et al., FZJ 1.
Nuclide inventories in Hg-targets
2.
Radiotoxic inventories of Hg targets
3.
Dose calculations for an accident-typical nuclide vector released from Hg targets
4.
Thermo-chemical studies of mercury/iodine system
5.
Hg toxicity: the legal situation as in 2003
TN-06-? “Thick target spallation residual products of the Hg and UCx”, B. Rapp et al., CEA Saclay + CERN, July 2006; SATIF-8 workshop TN-06-? “Dose estimates and shielding design for the EURISOL facility”, M. Felcini et al., CERN, August 2006; SATIF-8 workshop TN-06-? “Activation of air, soil and ground water for the EURISOL facility”, B. Rapp et al., CEA Saclay + CERN, August 2006 …
Work is in progress by CERN, CEA, FZJ
15 June 2006, PSI, Switzerland; contact:
[email protected]
Sub-task A; M1.2; radiation and activation Safety & Radioprotection
Geometry 2006
p(1GeV; 4MW) Hg UCx
Total activity
3
H
148Gd
Importance of model validation-benchmarking! 15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task A; M1.3; shielding guidelines
Action
Leading institute & support
Planned
1. Proton driver
CERN (support CEA/FI)
Month 24
2. TIS and beam dump
CERN (support CEA/FI)
Month 24
3. Mass separator and post-accelerator
CEA (support CERN/NIPNE)
Month 36
4. Experimental halls
CEA (support CERN/NIPNE)
Month 36
Note: 4 MW and 100 kW targets are addressed.
Collaboration with all corresponding tasks is crucial!
“Proton driver” and “Target assemblies” 1 feasible by 2007 2
Not sufficient information for “3” and “4” ! 3 • beam ions/energy/intensity and expected losses • simplistic geometry/material configuration 15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task A; M1.3; shielding guidelines
15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task A; M1.3; shielding guidelines (example from ESS by P. Berkvens et al. (2006))
42 458 462 49 7 9 8 7 2 8738 17 28 962 888µ 1234546475873829 68 42 45837 898425875 26286452 800 height earth berm [cm]
700 600 500 400 300 200
Cross check: MC versus deterministic
100 0 -1500
-1000
-500
260 cm
0
500
300 cm
300 cm
300 cm
60 cm
15 June 2006, PSI, Switzerland; contact:
[email protected]
1000
position from beam axis [cm]
42 45 6452
"88 75 2628#8 "$8829 6
%75628 '9
7
!8µ
%7&2 8 72
8µ
Sub-task A; M1.3; shielding guidelines (example from CERN by T. Otto et al.)
Safety & Radioprotection
Point source, line-of-sight attenuation formula
R
123456789 585 8758 8 88 7 687885
Z • •
R
RIB to ioniser/separator
Z
graphite
UCx targets 4 MW proton beam
• far shielding (?) • close shielding (?)
mercury
UCx targets
Only 2 m of iron shielding are represented To be complemented with concrete and/or earth
used target to hot cell
graphite 1m
15 June 2006, PSI, Switzerland; contact:
[email protected]
Bulk shielding can be planned with line-of-sight formulae!
Safety & Radioprotection
2006: sub-task B
• activity dispersion, contamination, migration • oxidation of target materials • containment of volatile radioactivity • target preparation, handling, confinements, ventilation • waste production • risk and failure scenarios ** Deliverable/
** Deliverable/Milestone Name
Milestone No
** Workpackage
** Lead
/Subtask No
Contractor(s)
** Planned in months
Expected in months
M2.1
Dispersion of radioactivity
5/B
LMU, NIPNE, CERN, FZJ, CEA
17
17 ok
M2.2
Test of purification system
5/B
LMU, CERN, NIPNE, FZJ, CEA
31
31
M2.3
Containment of radioactivity
5/B
LMU, CERN, NIPNE, FZJ, CEA
17
17 (ok)+3
M2.4
Activity transport in ground water
5/B
LMU, FZJ, CEA
17
17 (ok) + 3
15 June 2006, PSI, Switzerland; contact:
[email protected]
FI,
Safety & Radioprotection
Sub-task B; M2.1: dispersion of radioactivity
TN-06-06 "Dispersion of radio-elements, contamination, migration: experience gained from NPPs“, Dan V. Vamanu, Valentin T. Acasandrei and Bogdan I. Vamanu, NIPNE Bucharest, Jan. 2006 + 1st version of the software available on CD SOURCE:
Oak Ridge National Laboratories. The CONDOS code. U.S. Nuclear Regulatory Commission, International RTM-95 Response Technical Manual
Exposure / Dose to distance Isotope / Mix
Shielding Lead Iron Aluminium Water Air Concrete
ECF DCF
• Exposure • EDE • BDE
OK: in time (NIPNE) 15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
Sub-task B; M2.3: Containment of radioactivity
(2 6)25 394 46&8968%**8+,9 45-
12 23 42 967
. &7/952 / 7676&/2870/ 2867812 408 23 42 967
. 34 6877 45862 6 82468 &7/952 02 30
3 955285246896475
. 29 0 2256873862/2 960 284 6 4)06475 /0/4589/946& 4 767/48 26945256 3967
79 459647589/9)4 46&84589 287389008 296 7525 9628)04 .0/80 458 7562 7/2 96475 /2 37 952 458/ 2 252873876834 4758 70 2 15 June 2006, PSI, Switzerland; contact:
[email protected]
OK: in time (LMU)
Safety & Radioprotection
Sub-task B; M2.4: activity transport in the ground water
764964758738 74 70582962 6 4 96475873896446&82468 70582962
898:; 4 756 4)06475 Main goal is the development of a code system for calculation of the groundwater contamination at the EURISOL fence (tap water quality is required there). 1
By preliminary activation calculations the most relevant nuclides were identified:
Air, soil and ground water activation (source) will be done shortly for typical soils at CERN, GANIL and FZJ!
OK: in time (FZJ, CEA) 15 June 2006, PSI, Switzerland; contact:
[email protected]
Safety & Radioprotection
2006: sub-task D
• licensing and permission procedures (country dependence) • guidelines on technical options, implementations and execution conditions • potential risk and delay estimates
** Deliverable/
** Deliverable/Milestone Name
Milestone No M3.1
Conformity to legislation
** Workpackage
** Lead
/Subtask No
Contractor(s)
5/D
GANIL, CERN, CEA, FZJ
Specific request by G. Fortuna: legal issues related to the use/production of 233U, 235U and 239Pu 1. 2. 3. 4.
For Switzerland: CERN 1 OK For Germany: FZJ 1 OK For France: GANIL 1promised For Italy: INFN 1 promised
15 June 2006, PSI, Switzerland; contact:
[email protected]
** Planned in months 45
Expected in months 45
Safety & Radioprotection
2006: sub-task D
The following handling/production/storage limits of fissile materials would require Nuclear Facility Authorizations/Licensing: • for construction, operation and decommissioning • constant supervision by the safety authorities • decree by the government • fall under the safeguard rules derived from the non-proliferation treaty • demonstration: if >10-4/year probability accident 2 accidental exposure < 1 mSv; Examples: PSI in Switzerland, ILL Grenoble in France, … Fissile Material
Switzerland
Germany
France
Italy
Pu-239, g
15-150
15
375
-
U-233, g
15-150
15
375
-
U-235, g
15-150
15
600
-
Total fissile, g
15-150
15
375-600
-
Final note: Proton accelerator with • Ep > 300MeV and • Pbeam > 0.5kW 2 subject to Nuclear Facility Authorizations in France 15 June 2006, PSI, Switzerland; contact:
[email protected]
Task 5: some propositions (CEA) Safety & Radioprotection
3 options tried: natU, natTh, enrichedU (93 %)
p(1GeV; 4MW) Hg UCx
Initial material
Fissions/s Actinides produced, g/year (for 1 MW) (for 4 MW; irradiation 210 days)
1
natUCx;
3.76 x 1014
239Pu
2
natThCx;
0.84 x 1014
233U
3
enrichedUCx;
5.26 x 1014
236U(3.9);
~ 13 kg 238U; 100 g 235U; V~ 5 L ~ 13 kg 232Th; V ~ 5 L ~ 200 g 235U; V ~ 1 L
15 June 2006, PSI, Switzerland; contact:
[email protected]
(39), 236U(1.4), 237Np(0.9)
(57), 233Pa(13), 231Pa(1.3) * modified geometry *
Meetings held in 2006
Safety & Radioprotection
Date 5-6.06.06
Title/subject of meeting T5-04-WU-05-06.06.06
Location WU
Number of attendees
Website address 10
http://eurisol.wp5.free.fr/
Meetings planned in 2006 12-13 October 2006, LMU, T5 + Saferib
External partners: ORNL and TRIUMF have already contributed External partners: KAERI and JAEA (former JAERI) to be invited in October
15 June 2006, PSI, Switzerland; contact:
[email protected]
Deviations from Annex 1
Safety & Radioprotection
Request by B. Rannou (GANIL): Advance of sub-task E “conformity to legislation” Planned in 4th year 1 shift to 2nd year, i.e. 2006 1 3
Request by T. Otto (CERN): 67.5 kEuros of “personnel” 1 "travel and subsistence“ Decision in the coming MB meeting in June 2006
Request by D. Ridikas (CEA): Delay in deliverable D1: “Radiation, activation and doses” Planned in 2006 1 expected 2007 15 June 2006, PSI, Switzerland; contact:
[email protected]