SAFERIB – Business Meeting - WP5

Oct 13, 2006 - Peter Thirolf, JRA-10 SAFERIB. SAFERIB – Business Meeting. Agenda: • Financial situation (2006/7). • Annual report: Procedure and deadlines.
99KB taille 6 téléchargements 60 vues
SAFERIB – Business Meeting SAFERIB

Agenda: • Financial situation (2006/7) • Annual report: Procedure and deadlines • Audit Procedure • aob (next meeting)

Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Financial Situation SAFERIB

EURONS 1. Annual Report still has not been approved by EC revisions required mainly due to Transnational Access to Large Scale Research Infrastructures no complaints about JRA reports issued latest news from EURONS coordination: OK from scientific officer, now waiting for financial officer 2nd prefinancing will not take place before final approval of report present resources: (unspent) reserves at institutions and at MANET ~30% of projected JRA requests for 2006 will be available

Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Financial Situation: Transfer 2006 SAFERIB Total [EUR]

1. Spent Transf. 31.12.05

GSI

78000

34000

25867

8133

GANIL

72000

38800

46002

INFN

75600

25200

CERN

78000

FZJ LMU

Name

SAFERIB

Scaled 13-24

Planned Transf. Transf.

51800

34533

26400

8800

-7202

27000

18000

25202

8401

0

25200

54800

36533

11333

3778

22000

0

22000

78000

52000

30000

10000

33600

22400

30757

-8357

13100

8733

17091

5697

87600

25200

3550

21650

56400

37600

15950

5317

61425

281100

187400 125975 41992

424800 167600 106175

Peter Thirolf, JRA-10 SAFERIB

Balance AIS M13-30

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Reporting Procedure 2006 Annual report for 1.1.-31.12.06:

SAFERIB

- basically same procedure can be used as last year (no complaints by EC): progress information to be delivered by Activity Coordinators to MANET financial information to be delivered by institutions to MANET no new templates will be issued by MANET for Activity Reports - important dates: 24.11. : progress information sent to Activity Coordinator 1.12. : Activity Report sent to MANET by Activity Coordinator 11./12.12. : EURONS PCC-Meeting in Groningen: discussion of Activity Reports, initiate revisions ? 20.12.: final Activity Report to MANET 15.1.07: Cost Statements from Institutions needed at MANET > all spending until 31.12. (including personnel) (“Put pressure on your financial officer” …) must be in time, check with your financial officer in advance !! Audit Certificate needed at same time !!! 10.2.07: Submission of Annual Report to Brussels Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Reporting procedure SAFERIB

Reporting basics: A Activity Report: - progress report: follows AIS structure - list of milestones/deliverables achieved - use and dissemination of knowledge (meetings, workshops, web..) > here your input is needed - feedback from last report: keep it short (no figures, no physics details) !

B Management Report: ‘Justification of the resources deployed’: > Cost Statement (Form C): financial officer of institution C Report on the Distribution of Resources: > MANET

D Detailed Implementation Plan of next 12 months > budget request for months 25-36 > based on AIS and Annex I of contract

Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Description of Work SAFERIB

Task T-J10-1: Radiation-correlated mechanical, thermal, electric material properties Subtask T-J10-1.1: Characterization of hot open fission source Subtask T-J10-1.2: Secondary radiation and activation by fast heavy-ion beams in thick targets Task T-J10-2: Migration of radioactivity Subtask T-J10-2.1: Reliability of codes Subtask T-J10-2.2: Release study Subtask T-J10-2.3: Soil/ground water activation Subtask T-J10-2.4: Technical concept to confine radioactivity Task T-J10-3: Technical concept to confine volatile radioactivity Task T-J10-4: Failsafe remote-controlled target manipulator

Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Milestones and deliverables Milestones:

Short title

M-J10-1.1

Properties of fission source prototype characterized Secondary radiation from thick targets Activation measurements and activation Calculations of components in the vicinity of thick In-flight targets Validation of reliability: isotope production codes Release study of radiologically important isotopes from target ion source Study of soil/ground water activation Concept to confine radioactivity Technical concept to confine volatile radioactivity Solution for radiation-hard , remote-controlled target manipulator

M-J10-1.2 M-J10-1.3

M-J10-2.1 M-J10-2.2 M-J10-2.3 M-J10-2.4 M-J10-3 M-J10-4

Date duei 12/06

Date accompl.

12/05 12/07

12/05

12/05 4/06 6/06 6/06 11/07 11/07

GANIL INFN

D-J10-1

Report on task T-J10-1 (material properties) Report on task T-J10-2 (migration of activity) Report on task T-J10-3 (containment of volatile activity) Report on task T-J10-4 ( remote-controlled manipulator)

12/07

Type Disseminati on level R/PU

12/07

R/PU

12/07

R/PU

12/07

R/PU

Peter Thirolf, JRA-10 SAFERIB

*

CERN

04/06 CERN 11/06 ? FZJ 10/06 ? GANIL

Date due

D-J10-4

Date delivered

10/05

Short title

D-J10-3

LMU GSI

SAFERIB

GSI

Deliverables

D-J10-2

Remark

( ) ( )

Remark

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

Other Business SAFERIB

Dissemination of results: - publications - conference presentations etc. - notify Activity Leader of any public actions - keep web links up-to-date !!

Acknowledge support by EU: i) This work was supported by the European Commission within the Sixth Framework Programme through I3-EURONS (contract no. RII3-CT-2004-506065). ii) Supported through EURONS (European Commission contract no. 506065)

Next Meeting: - where and when ?

Peter Thirolf, JRA-10 SAFERIB

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

LMU@SAFERIB: Implementation Plan SAFERIB

Budget and personnel: Requested /kEUR : (1.1.07-31.12.07) month 25-36 Personnel: Travel: Consumables:

Peter Thirolf, JRA-10 SAFERIB

33 4 2.5

Spent /kEUR: (until 30.9.06) 11.0 3.0 1.1

Request / kEUR (1.1.06-30.6.07) month 13-30 40 4 3.5

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006

EURISOL-DS (WP5): LMU Budget Situation in 2006

SAFERIB

Budget and personnel: Request/kEUR : (1.2.06-31.1.07) Personnel: Travel: Consumables:

Peter Thirolf, JRA-10 SAFERIB

59 3 15

Spent /kEUR: (until 30.9.06) 45 1 3.5

Request / kEUR (1.2.07 –31.1.08) 45 4 15

2. Annual SAFERIB/EURISOL-DS (T5) Meeting, Munich, 12./13. October, 2006