Page 1 - CFMS

Control of works dependant on obtaining pertinent data and acting on it. Unable to obtain critical .... Survey 3 months before arch raising. – Initial 6 weeks survey ...
922KB taille 13 téléchargements 258 vues
Exploring the limits of the Observational Method 1. Background – key requirements for OM

2. New Wembley Stadium – raising the arch (pile group behaviour)

3. Limehouse Basin

Exploring the limits of the Observational Method

– a step too far? (retaining wall behaviour)

4. Earthworks asset management – the weakest link? (degradation of clay fill embankments)

Tony O'Brien BGA/CFMS Seminar, Paris - December 2011

Key factors for Observational Method implementation

Key requirements for OM Peck (1969) outlined 8 requirements !

Adverse factor

– Exploration (or Ground Investigation) – Assessment of variations in conditions - most probable and most unfavourable [now - use of "progressive modification"] – Design basis – Key observations and predictions (most probable)

Adequate warning when approaching a ULS?

Progressive collapse

Failure of one component, leads to rapid failure of overall system

Lack of stakeholder support

All parties in project need to be actively involved and supportive

Unable to obtain critical observations reliably

Control of works dependant on obtaining pertinent data and acting on it

Implementation of contingency measures is too slow

The contingency plans need to be fully developed and able to be implemented within the available timescale

Contract conditions

Appropriate?

– Key observations and predictions (most unfavourable) – Design modifications for every foreseeable scenario – Make observations and evaluate actual conditions

Comment

Brittle failure

– Modify design based on observations

Page 1

New Wembley Stadium - raising the iconic arch

Demolition and site preparation

Retaining walls, shear cores and arch fabrication

Raising the arch

! arch: 133m high, 315m span ! longest single span roof structure in the world

Page 2

! key concern: arch buckling " pile group deformation critical

! risk management " use of OM (OM rare for pile groups)

Raising the arch Concerns !

!

Lifting mechanism – side elevation Risk management - use of OM

if any pile group was to move excessively, due to its slenderness, the arch may buckle no case histories exist for pile groups of this size subjected to complex load combinations vertical, horizontal moment and torsion

!

complex for piled foundations

!

use of non-linear boundary element analysis

Turning Struts

Arch at Original Position

Turning Struts .

Jacking Points

Jacking Points

Arch Stillage Base

– allowable movement dependent on load combination !

– pile group displacement

instrumentation and observation of pile groups

!

consideration of failure/deformation mechanisms

!

contingencies

Jacking Points

– kentledge – tie backs to shear cores

Piled Foundations

Original Position of Arch

180000 Vertical

! many load cases – 13 different angles – 9 per angle

x (+ve east)

! lack of case history data Turning Struts

– lateral/moment loading

Jacking Bases

Horizontal

160000

Moment

Moment / Force (kNm / kN)

Western Arch Base

+ve x rotation

y (+ve north)

Restraining Lines

Restraining Lines

Challenges example of complex loads, eastern arch base

Lifting mechanism – plan view Eastern Arch Base

Arch in Final Position

Arch in Vertical Position

– structural forces

!

Torsion

140000 120000 100000 80000 60000 40000 20000 0 0

Pile group configurations

10

20

30

40

50

60

70

Arch Angle (degrees)

! temporary base pile groups vary from 6 to 12, 1.5m dia piles ! pile length varied from 10 to 42m

Page 3

80

90

100

110

120

Shear modulus vs. Depth

Site geology and topography Old Concourse

Seismic cone and self-boring pressuremeter Old Concourse

Old Wembley Pitch Area

South Way

Shear Modulus at Small Strain (MN/m2)

Chiltern Marylebone Railway Line

0

BH201A/201B DH202 60

BH205

WS7

BHC1

BHB2

BH6

BH204

BHB3 BH203

Depth below Top of London Clay (m)

BH3

Made Ground IVa IIIb IIIa

Reduced Level (m AOD)

50

IIIb

IVb IIIc IIIa IIa

40

IIIb IIIa IIb IIa

IIIa IIa/b

30

Ib

A

Ib

dw

w ater flo

B B

IIIa

Ia Gro un

IIb

20

IIIb

Unweathered London Clay

Ib Ia

A

B

B

A

A

Unit B Unit A

Ib

IIa

Weathered London Clay

IIIb IIIa

10

Lambeth Formation 0

Upnor Sands

! site history

! deep weathering of London Clay

– influence of old stadium

– 8 to 10m

! topography

! hence, may be differences in London Clay behaviour across site and c.f. central London

– on top of hill, adjacent rail cutting

Analysis Type

Lateral pile test results

Vertical Horiz. Stiffness Stiffness (MN/m2) (MN/m2)

100

200

300

400

0 5

Weathered London Clay

SBP

10

SCPT

Unweathered London Clay

15

Unit B

20 25

Unit A

30 35

Lambeth Group

40

Lateral test pile results

232

171

! initial tangent stiffness, assumed anisotropic

400

– vertical - seismic cone

300

– horizontal - SBP

200

Back analysis using linear elastic model

100

500

0

Stiffness at FOS = 1.7

0

20

40

60

80

Lateral Movem ent (mm )

118

23

Eh drops by 19x during loading ! #Eh >> #Ev

Stiffness at Failure

60

9

Horizontal Load (kN)

Initial Linear Stiffness

Horizontal Load (kN)

500

Test Data

400 300 200

Non-linear 100

Single pile testing 0

Non-linear analysis essential for large lateral loads

0

20

40

L ateral M o vem en t (m m )

Page 4

60

80

The use of the observational method Identifying threshold limits

application to piled foundations

Load combination A

1. 121 Load combinations for each pile group

Load combination B

! Displacements

Movement

Red Limit

! Structural forces (BM/SF/Axial) in piles [CRITICAL]

2. Red Limit

Amber Limit

a) Full load combination (Horizontal force/overturning moment/etc) x Factor ! Failure of a pile in group b) (Dominant load only) x Factor ! Failure of a pile in group

Angle of Arch

Allowable movement dependent on load combination !

Worst of a) and b) " Red Limit (two-thirds of ultimate structural capacity)

Identifying threshold limits

Predicted x Rotation for eastern arch base 25

3. Amber Limit

Red Limit

20

x rotation (mdegs)

4 Criteria ! a) Predicted pile group deformation - most likely load combinations + plausible ground stiffness variations (± 25%) b) Sufficient "distance" between Amber + Red to facilitate timely implementation of contingencies c) Sufficiently beyond "expected" deformation to avoid regular breaches of Amber limit

Amber Limit

15 10 5 0 0 -5

d) Deformation monitoring accuracy

20

40

60

80

Repute Non-Linear

Repute Linear Run 1

Repute Linear Run 2

Repute Linear Run 3

-10 Angle of Arch (degrees)

Non-linear analysis - essential

Page 5

100

120

Monitoring strategy

Raising the arch Jacking initially applied 14MN at each JP

! Vary load at each jack to maintain arch alignment

! primary system – precise levelling (± 0.1mm) and surveying (± 1.5mm)

! torsion to pile group

– had to measure small movements accurately – Survey 3 months before arch raising – Initial 6 weeks survey accuracy improved, ± 5mm ! ± 1.5mm

! secondary system – electrolevel beams, selected pile groups

A critical risk "brittle" failure of corner pile

Risk mitigation

Movement

(combined tension and shear) due to torsional loading

Unacceptable and unsafe, "brittle" ; no time for contingency

OM contingency measures (pre-designed)

Unacceptable but safe trend, "ductile" ; use contingency

! apply large "kentledge", put corner pile into compression ! ductile mechanism ! other contingencies D u c t ile S tru c tu ra l f a ilu r e

– install and pre-stress tie backs F o rc e

– modify jacking forces

Angle of Arch

! if adverse trend

! brittle mechanism

– pile specific capacity checks for current (rather than critical) load combination

– occur at small displacement – no warning – unacceptable

Page 6

B rittle S tru c tu ra l fa ilu re

Construction of the arch

Pin at eastern arch base

Monitoring results

– initial elastic stiffness: SBP and Seismic Cone – calibration vs single pile tests – scale up to 1.5m dia and model Pile Group

!

monotonic loading – good prediction

!

load reversal – underpredict (but anticipated!)

!

monitoring data overload? – 72 graphs per arch lift increment

Page 7

East Arch Base

predictions: non-linear (hyperbolic) analyses

14

Horizontal y Movement (mm)

!

12

Surveyed Non-Linear

10 8 6 4 2 0 -2

0

20

40

60

80

-4

Angle of Arch (degrees)

100

120

Predicted and observed horizontal movement in the x direction of eastern arch base

Predicted and observed z rotation of eastern arch base

40 30

7

20 6

z rotation (mdegs)

Horizontal x Movement (mm)

8

5 4 3 2 Surveyed Non-Linear Repute

1

10 0 -10 0

20

40

40

60

80

100

100

120

-30 -40 Surveyed Non-Linear Repute

-60 20

80

-50

0 0

60

-20

-70

120

Angle of Arch (degrees)

Angle of Arch (degrees)

Arch roll up phase 3 - OM successfully implemented

Limehouse Basin ! old project (early 1990's, but important lessons on "limits" of OM

Page 8

Limehouse Basin

Limehouse Basin

! OM introduced - eliminate the need for mid-height props?

! load on cofferdam – mainly groundwater pressure (control of water levels in fill?)

! failure mode – excessive bending of sheet pile wall

! critical measurements – complex due to stiffness contrast between N. wall ("stiff" steel tubes) and S. wall ("soft" sheet piles) – (absolute wall movement not wall convergence)

Granular fill London Clay Woolwich and Reading Beds

Progressive modification ! soft prop trial - gap at "safe" wall displacement limit ! risks associated with OM ! too high Top prop Sheet pile wall

! OM did facilitate project benefits – Phase 2 - construction sequence changed

Soft prop trial

Original

Gap closed in 7 to 10 days. Inadequate time for base slab construction

After OM

Exc. to mid-height prop

Excavate to base slab level

Install mid-height prop

Install mid-height prop

Exc. to base slab level – Phase 3 - reduction of sheet pile wall embedment, from 4m to 0.5m reduced sheet pile damage, hard driving

Lambeth Group

reduced risk of declutching of sheet piles

Page 9

Earthworks asset management Potential for long term (decades) application of OM?

! most of UK rail network built >100 years ago ! embankments - end tipping of clay fill ! increasing problems of delayed failure and excessive track deformation

Deep Seated Delayed Failure of Railway Embankment (6m high Grass Covered Slope)

Track Deformation. Seasonal Movement of Railway Embankment (Mature Tree Covered Slope)

‘Fatigue’ failure of high PI clay fills

Field observations indicate embankment deformation critically influenced by

Consequence of seasonal changes in pore water pressure Toe is critical area

Discontinuous shear surface

! Climate ! Vegetation

Development of shear surface due to shrink swell progressive failure

– eg. High water demand trees on slope or grass covered slope

P e a k

P o s t

r u p t u r e R e s i d u a l

High plasticity clay, post-peak strain softening NB Mechanism observed in both numerical and centrifuge modelling and in field Development of Reidel Shear Zones

Page 10

Long term Observational Method applications - Challenges

Can OM lead to more cost-effective stabilisation? Complexity of ground movements

Normal seasonal movements vs. Movements prior to failure. Can we differentiate?

! site access often difficult ! local environmental constraints

Speed of contingency measure implementation vs. speed of failure (days/weeks)

! duration and cost of monitoring (decades) ! organisational/human challenges ! communication and control over long term

Pound Green Tree removal during instrument installation

Crest Extensometer

! potential to save money vs. cost of OM

Numerical modelling shown wide range of movements may be acceptable, depending on local conditions

Exploring the limits of the Observational Method

Exploring the limits of the Observational Method

Conclusions

Conclusions

1. OM for pile groups - raising the Wembley Arch

2. Limehouse Basin - a step too far

! !

– pile groups, intrinsically stiff structures

– OM benefits outweighed by risks

– monitoring system, reliable measurement of small movements

– BUT

– threshold limits (amber/red), depend on load combination

– introduction of OM created opportunities:-

– simple contingency, rapidly implemented

– improved construction sequence – reduced wall embedment

challenging application! !

OM successful for managing risk during a unique task

Page 11

hence, cost and time savings still achieved!

Exploring the limits of the Observational Method

Overall

Conclusions 3. Earthworks asset management - the weakest link? Long term application of OM

Conclusions Reliability of key measurements

Mode/magnitude of deformation

– delayed failure of clay embankments

Speed of response

Type of failure mechanism

– potential need for very long term application (decades)

"Team" communication

Team organisation/interfaces

– prime challenge is human rather than technical ie. Ability of any organisation to apply OM over many years

(OM successful for cutting stabilisation, short term during construction)

Page 12

Human vs Technical Issues