foundations of monestier viaduct - CFMS

Bellow P3 and P4, varved clay which is water saturated, is present up to 80m deep. Ground is therefore not stiff enough to carry heavy loads. The design of the ...
5MB taille 7 téléchargements 316 vues
A51 : MONESTIER DE CLERMONT VIADUCT

FOUNDATIONS OF MONESTIER VIADUCT • • •

Dominique Quivy Laurent Bastard-Rosset Michel Londez

VINCI Construction France GTM TP Lyon Independent expert Mécasol

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

PARTNERS

 Contracting Authority

Les Autoroutes Rhône-Alpes

 Design and built joint

GTM TP Lyon, mandatary

venture

Geotechnical engineering

 MECASOL

Civil engineering design office

 VINCI Construction B.E.T.

Architect : Jean-Vincent

 STRATES

Berlottier

 PAYSAGE PLUS

Landscape painter

 BAUDIN-CHATEAUNEUF

Structural steel Construction MONESTIER DE CLERMONT VIADUCT

PLANNING

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

GEOTECHNICAL ENVIRONMENT Michel LONDEZ

MONESTIER DE CLERMONT VIADUCT

Chemin de fer

Geological Cross section

Rock

Moraines

P5

P6

grey clay

Rock Varved clay

vvy

Moraines Rock Clay and blocks

Sliding Area

MONESTIER DE CLERMONT VIADUCT

Chemin de fer

PIERS SETTING OUT

MONESTIER DE CLERMONT VIADUCT

SLIDING ZONE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 FOUNDATIONS CONSTRUCTION Laurent BASTARD-ROSSET

MONESTIER DE CLERMONT VIADUCT

FOUNDATIONS Five different types of foundations :  C0 & P1 : Large pits (4 m diameter)  P2 : Concrete piles (1,5 m diameter)  P3 & P4 : semi-deep Foundations

C0

P1

P2

P3

P4

 P5 & P6 : Piles inside circular diaphragm wall  P7, P8 & C9 : Spread footing

P5

MONESTIER DE CLERMONT VIADUCT

P6

P7

P8

C9

P3 & P4 FOUNDATIONS

P3

Bellow P3 and P4, varved clay which is water saturated, is present up to 80m deep. Ground is therefore not stiff enough to carry heavy loads. The design of the foundations is quite unusual : the principle consists in taking off a quantity of clay equivalent to the load brought by the pier itself (weights of the foundation + pier + deck ).

MONESTIER DE CLERMONT VIADUCT

P3 & P4 FOUNDATIONS

raft

22 m 20 m

Steel inclusions

diaphragm wall

P3 FOUNDATION INCLUDES : - a diaphragm wall (20m diameter and 22m deep). - 20m long steel profiles (HEA 300) driven into clay - a 1,50m thick concrete slab, poured above a 1,00m thick gravel layer. - 80cm thick concrete walls stiffening the structure and allowing transfer of pier load to the diaphragm wall and concrete slab. - The inside volume (1700m3) remains empty except during construction of the pier when it is filled with water.

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS GROUND EXTRACTION

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS GROUND EXTRACTION

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS REINFORCEMENT AND CONCRETE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STEEL PROFILES DRIVEN INTO CLAY (STAGE 1)

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : CLAY EXCAVATION INSIDE DIAPHRAGM WALLS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : FINAL PREPARATION FINAL PREPARATION OF THE GROUND BEFORE GRAVEL LAYING OPERATIONS AND CUTTING BACK OF STEEL PROFILES

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STATE OF THE FOUNDATION JUST BEFORE GRAVEL IS LAY DOWN

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : GRAVEL LAYER AND PIEZOMETER IN PLACE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : REINFORCEMENT OF CONCRETE SLAS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STIFFENING STRUCTURE WALLS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : GENERAL VIEW

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS CALCULATIONS Michel LONDEZ P3CPT3 -20.000

0.000

20.000

40.000

Cu (kPa)

0 0

50

100

150

200

0.000

- 10

-20.000

P ro f o n d e u r (m )

- 20

- 30

-40.000

- 40

- 50 -60.000

- 60

C (qt/12)

C (qt/10)

Pressiomètre P3S2

¨Pile 3 - Radier à -7m/TN Point sur la paroi

50 Consolidation

Numéro des pas de calcul

40

Mise en place de la charge de service

Ouvrage terminé Vidange de la fouille effectuée 30 Radier Relachemenent nappe 20 Avant clavage+ remplissage

Fin de mise en place du gravier

10

Fin d 'excavation 0 -0,09

-0,07

-0,05

-0,03

-0,01

0,01

Tassements de la paroi (m) P3C1CasA

MONESTIER DE CLERMONT VIADUCT

P3C1CasB

P3C1CasC

0,03

0,05

THE STUDIES Survey program

 P3 to P6  Core borings,  CPTU 65 m deep  Pressiometric tests  Cross hole  Pumping test  Inclinometres  Laboratory tests

MONESTIER DE CLERMONT VIADUCT

MAIN RESULTS



Accross the valley:



South west area: - Rock at 50 m. - Fluvio-glacial permeable till between 40 à 50 m - Gravelly clays below soft and remolded clays



Centre and north of the valley: - Deepening of rock (P2) - Argiles homogeneous clays at the surface, varved below

MONESTIER DE CLERMONT VIADUCT

GEOLOGICAL PROFILE

Chemin de fer

Geological Cross section

Rock Moraines

grey clay

Clay and blocks

varved clay Varved stiffer clay Rock

ClSliding Areay and blocks MONESTIER DE CLERMONT VIADUCT

Rock Rock

PENETRATION TEST FOR P3

MONESTIER DE CLERMONT VIADUCT

CU (KPA) FROM CPTU AND PRESSURMETRES P3CPT3 Cu (kPa)

0 0

50

100

150

- 10

P ro f o n d e u r (m )

- 20

- 30

- 40

- 50

- 60

C (qt/12)

C (qt/10)

Pressiomètre P3S2

MONESTIER DE CLERMONT VIADUCT

200

OCR FOR P3 P3CPT3

1

1,5

2

0

- 10

- 20

- 30

- 40

- 50

- 60

MONESTIER DE CLERMONT VIADUCT

2,5

OCR

3

FOUNDATION OF BEARINGS P3 & P4

The foundations of P3 and P4 include : - a cylindral skirt made of diaphragm wall, 20m diameter and 22 to 26 m deep. - A 1,50m thick concrete slab - Steel inclusions (HEA 300), down to 20m below the slab, - Stiffening walls 80cm thick to tranfert the shaft efforts to the slab and the diaphragm walls An inner volume of 1700m3 above the slab remains empty.

MONESTIER DE CLERMONT VIADUCT

Steel profiles setting out

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Strength C’ (KN/M2)

φ’(°)

OCR

Depth (m)

Type of soil

18.5

5

24

σ’0+50 KN/M2

0 - 18

Upper clay

18.5

0

24

σ’0

18 – 37/55

Medium clay

18.5

10

30

37/55 80

Lower clay

Volumetric mass(KN/M3)

1.2 σ’0

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Deformation CASE A

CASE B

CASE C

Triaxial Interpretation

Oedometric Interpretation

Oedometric method

Soil

E50réf (kN/m2)

Eoedréf (kN/m2)

E50réf (kN/m2)

Eoedréf (kN/m2)

Cc/1+e

Cg/1+e

7500

6000

3150

2500

0.12

0.024

Upper clay

7500

6000

3150

2500

0.12

0.024

Medium clay

7500

6000

7500

6000

MONESTIER DE CLERMONT VIADUCT

Hardening Model

Lower Clay

CALCULATION MODEL -20.000

0.000

20.000

0.000

-20.000

-40.000

-60.000

MONESTIER DE CLERMONT VIADUCT

40.000

SEQUENCES OF CALCULATIONS

• Excavation of a mass of soil close to the estimated load brought by the pier • Inclusions to control the soil relaxation , reduce the recompression settlement • Maximum loads during construction ( pre-loading with water) • After final bearings installation, settlements calculations under final loads and surcharges, consolidation. • Acceptable differential settlements between piers: 6 cm.

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS ESTIMATIONS

Design loads Settlements in mm

Calculation Cases

Soil parametres

Raft construction

Loads without Superstructures + water

Total + service loads + Consolidation

P3

P4

P3

P4

P3

P4

A

Triaxial interpretation

5

6

33

35

21

21

B

Triaxial interpretation*0.42

7

6

62

56

50

38

C

Oedometric model

7

7

50

44

30

35

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Deformation CASE A

CASE B

CASE C

Triaxial Interpretation

Oedometric Interpretation

Oedometric method

Soil

E50réf (kN/m2)

Eoedréf (kN/m2)

E50réf (kN/m2)

Eoedréf (kN/m2)

Cc/1+e

Cg/1+ e

7500

6000

3150

2500

0.12

0.024

Upper clay

7500

6000

3150

2500

0.12

0.024

Medium clay

7500

6000

7500

6000

MONESTIER DE CLERMONT VIADUCT

Hardening Model

Lower Clay

OBSERVATIONS DURING CONSTRUCTION

MONESTIER DE CLERMONT VIADUCT

OBSERVATIONS DURING CONSTRUCTION

MONESTIER DE CLERMONT VIADUCT

COMMENTS

• For P3, settlements during construction were close or slightly higher than those estimated with the triaxial interpretation (case A) • Needs for setlements reductions have been estimated necessary • Adaptations of the design have been done: - Preload with water, removed when superstructures have been completed. - Deck level set out 20 mm above designed level to increase the acceptable differencial settlements to 80 mm instead of 60 mm initialy considered in the design. • For P4, the setlements are much lower due to the longer length of the diaphragm wall skirt.

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS VERSUS TIME

MONESTIER DE CLERMONT VIADUCT

Comparison between estimations and observations Settlements in mm

End of construction

Estimations Observations

In service

P3

P4

P3

P4

33 to 62

37 to 56

21*

21*

11.5**

13.5**

37

19

•* End of consolidation~ 80 years •** After ~4 years: Consolidation not completed • **To be compared to 80 mm acceptable differential settlements

MONESTIER DE CLERMONT VIADUCT